How to wire PV modules correctly

Wiring photovoltaic (PV) modules isn’t just about connecting A to B—it’s a precision task that demands attention to electrical compatibility, safety, and system efficiency. Whether you’re setting up a residential rooftop array or a ground-mounted system, the process starts with understanding your modules’ specifications. Check the nameplate ratings for voltage, current, and power output. Mismatched voltages between modules and inverters can lead to energy losses or even equipment damage. For example, if your inverter’s maximum input voltage is 600V, ensure the combined open-circuit voltage of your series-connected modules stays below this threshold, especially in cold climates where voltages can spike.

Begin by planning the wiring configuration: series or parallel. Series connections increase voltage while keeping current constant, ideal for systems with long wire runs to minimize energy loss. Parallel connections maintain voltage but add current, which requires thicker, more expensive wiring. For large systems, a hybrid approach—series-parallel—is often optimal. Let’s say you have 20 modules: arranging them into four series strings of five modules each, then connecting those strings in parallel, balances voltage and current efficiently. Always use a combiner box with properly rated fuses or breakers when merging parallel strings to prevent overcurrent scenarios.

Cable selection is non-negotiable. PV wire (UL 4703-rated) or USE-2 cables are mandatory for outdoor installations due to their UV resistance and insulation durability. For a 10A circuit, 12 AWG copper wire is standard, but derate for temperature—if ambient temps exceed 30°C, upsize to 10 AWG. Use polarized MC4 connectors for module interconnections, and crimp them with hydraulic tools—not pliers—to ensure airtight contacts. Loose connections create hotspots that degrade performance over time. When routing cables, leave drip loops near entry points to prevent water ingress into junction boxes.

Grounding is legally required and technically critical. Each PV module frame must bond to the system’s grounding electrode conductor using stainless steel hardware to resist corrosion. In the U.S., comply with NEC Article 690.43, which specifies a minimum 6 AWG copper grounding conductor for most residential systems. For rail-mounted arrays, use listed grounding clips that bite into the aluminum rails—no drilling or self-tapping screws, which void corrosion warranties.

Before energizing the system, test every circuit. Use a digital multimeter to verify open-circuit voltage matches the sum of individual module voltages (±5% tolerance). Check for reverse polarity by measuring voltage at the inverter terminals—negative readings indicate swapped connections. Perform insulation resistance tests with a megohmmeter: 1,000V applied between live conductors and ground should show at least 1 MΩ resistance. Document these values; they’re your baseline for future maintenance.

For complex installations, consider PV module optimizers or microinverters. These devices allow module-level maximum power point tracking (MPPT), which boosts yield in shaded or unevenly oriented arrays. When retrofitting older systems, ensure new modules have compatible voltage and current characteristics with existing ones—mixing dissimilar modules can drag down entire strings.

Weatherproofing is your final defense. Seal all conduit entries with duct seal compound, not just cable glands. Apply antioxidant gel to aluminum busbar connections in combiner boxes—aluminum oxidizes faster than copper. For rooftop penetrations, use flashing kits with EPDM or butyl rubber gaskets that outlast standard silicone. In snowy regions, maintain at least 6 inches of clearance between module lower edges and roof surfaces to prevent ice dam interference.

Seasonal adjustments matter. In high-temperature areas, leave extra slack in module interconnection cables—conductors expand in heat. For windy locations, secure cables every 18 inches with UV-resistant zip ties. Annual maintenance should include thermal imaging scans to detect failing connections and I-V curve tracing to spot underperforming modules. Keep vegetation trimmed back—partial shading from a single branch can cut string output by 30%.

Never overlook local codes. The 2023 NEC requires rapid shutdown systems that reduce conductor voltages to 30V within 30 seconds of shutdown activation. This means installing listed rapid shutdown devices either at the modules or within 1 foot of them. Label all DC conductors every 10 feet and at termination points with “PHOTOVOLTAIC POWER SOURCE” in durable, sunlight-resistant markers.

Lastly, document everything: module serial numbers, string configurations, torque values (typically 35-45 in-lb for MC4s), and test results. This paperwork isn’t just for inspections—it’s invaluable when expanding the system or troubleshooting. With modules now pushing 600W+ outputs, precision wiring isn’t optional; it’s the backbone of a safe, high-yielding solar investment.